PMP · Question #45

The project manager is reviewing a project's progress and notices that one of the risks has become an issue. What should the project manager do to address the situation?

The correct answer is B. Meet with the project team and customer to brainstorm about potential solutions. A identified risk has materialized and become an issue during project progress review.

Submitted by obi.ng· Apr 18, 2026People

Question

The project manager is reviewing a project's progress and notices that one of the risks has become an issue. What should the project manager do to address the situation?

Options

  • AInitiate a change request to obtain additional funds from the management reserve
  • BMeet with the project team and customer to brainstorm about potential solutions
  • CSchedule a high-priority meeting with the project stakeholders to discuss the issue
  • DCollaborate with the relevant stakeholders on implementing the risk response plan

How the community answered

(26 responses)
  • A
    4% (1)
  • B
    85% (22)
  • C
    8% (2)
  • D
    4% (1)

Why each option

A identified risk has materialized and become an issue during project progress review.

AInitiate a change request to obtain additional funds from the management reserve

Initiating a change request for additional funds is premature before a solution has been defined, and the specific resource implications of addressing the issue are understood.

BMeet with the project team and customer to brainstorm about potential solutionsCorrect

When a risk materializes into an issue, the project manager must understand the full impact and explore potential solutions collaboratively. Meeting with the project team, who are closest to the work, and the customer, who is directly affected, to brainstorm solutions is a crucial first step to define the best path forward and gain buy-in for addressing the issue.

CSchedule a high-priority meeting with the project stakeholders to discuss the issue

While informing stakeholders is important, it is more effective to first develop potential solutions with the team and customer rather than immediately escalating to a larger stakeholder meeting without a proposed course of action.

DCollaborate with the relevant stakeholders on implementing the risk response plan

This implies an existing risk response plan is directly applicable and simply needs implementation; however, if a risk becomes a full 'issue,' it often indicates the need for more dynamic problem-solving or a workaround beyond a pre-planned response, which brainstorming facilitates.

Concept tested: Issue management and problem-solving

Topics

#Risk Management#Issue Management#Team Collaboration#Stakeholder Engagement