nerdexam
PMI

PMP · Question #383

A new regulation has been approved that will impact the deliverables in the fourth phase of the project. The delivery is following an iterative approach and is currently completing the second phase. W

Sign in or unlock PMP to reveal the answer and full explanation for question #383. The question stem and answer options stay visible for context.

Submitted by miguelv· Apr 18, 2026Business Environment

Question

A new regulation has been approved that will impact the deliverables in the fourth phase of the project. The delivery is following an iterative approach and is currently completing the second phase. What should the project manager do next?

Options

  • AConsult with the project sponsor to discuss a cost increase
  • BAcquire approval for an exception to the implementation of the new regulation
  • CGet approval for the additional budget from the steering committee
  • DMeet with subject matter experts (SMEs) to access the impact to objectives

Unlock PMP to see the answer

You've previewed enough free PMP questions. Unlock PMP for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.

Topics

#Change Management#Impact Assessment#Regulatory Compliance#Stakeholder Engagement
Full PMP Practice