PMIPMI
PMP · Question #312
PMP Question #312: Real Exam Question with Answer & Explanation
Sign in or unlock PMP to reveal the answer and full explanation for question #312. The question stem and answer options stay visible for context.
Submitted by jaden.t· Apr 18, 2026Process
Question
A project manager is leading a project that is in an advanced stage. All high-level risks identified in the risk management plan have been resolved or are no longer a risk for the project. Only low- level risks remain. What should the project manager do now?
Options
- AReclassify low-level risks as high-level risks.
- BNotify stakeholders that all high-level risks have been resolved.
- CReduce the priority of project risks as all remaining risks are low-level.
- DReevaluate identified risks and update the risk register.
Unlock PMP to see the answer
You've previewed enough free PMP questions. Unlock PMP for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.
Topics
#Risk Management#Risk Register#Continuous Monitoring#Risk Reevaluation