PMP · Question #222
PMP Question #222: Real Exam Question with Answer & Explanation
Sign in or unlock PMP to reveal the answer and full explanation for question #222. The question stem and answer options stay visible for context.
Question
A project scope statement has been approved, and the project manager and core team have been assigned to the project. Suddenly, the project manager takes a temporary leave of absence due to a medical emergency. While the project manager is on leave, the team develops the project schedule. When the project manager returns, a detailed schedule is almost complete. What should the project manager do?
Options
- AEnsure that the schedule is aligned with the vision and objectives.
- BEscalate the compliance issue to the project management office (PMO).
- CCongratulate the team and move on to the execution phase.
- DDevelop a new detailed schedule with the team and project sponsor.
Unlock PMP to see the answer
You've previewed enough free PMP questions. Unlock PMP for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.