nerdexam
PMIPMI

PMP · Question #223

PMP Question #223: Real Exam Question with Answer & Explanation

Sign in or unlock PMP to reveal the answer and full explanation for question #223. The question stem and answer options stay visible for context.

Submitted by krish.m· Apr 18, 2026Process

Question

A project manager manages a bridge construction project. The project manager has received a major change request from a regulatory stakeholder to add one branch of the bridge to the engineering design. The project manager prepared a change request, which was reviewed and accepted by the change control board (CCB). What should the project manager do now?

Options

  • ANotify the project team about the change request's approval.
  • BInclude the new branch of the bridge in the design.
  • CCommunicate the decision to the stakeholder who requested the change.
  • DEvaluate the adjustments to the project management plan.

Unlock PMP to see the answer

You've previewed enough free PMP questions. Unlock PMP for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.

Topics

#Integrated Change Control#Change Request Implementation#Project Document Updates
Full PMP PracticeBrowse All PMP Questions