PMIPMI
PMP · Question #178
PMP Question #178: Real Exam Question with Answer & Explanation
Sign in or unlock PMP to reveal the answer and full explanation for question #178. The question stem and answer options stay visible for context.
Submitted by yasin.bd· Apr 18, 2026Process
Question
A project manager entered into a contract with a vendor to build a new system. During the acceptance test stage, the project manager noticed that the system quality was not satisfactory. How should the project manager support their claim to the vendor?
Options
- AProvide the failed test results along with the agreed-upon acceptance criteria.
- BShare unsuccessful results from previous projects with a similar scope.
- CDocument in the risk log that the issues in the system were already identified.
- DShow that the acceptance criteria were changed by the vendor without approval.
Unlock PMP to see the answer
You've previewed enough free PMP questions. Unlock PMP for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.
Topics
#Acceptance Testing#Quality Management#Procurement Management#Contract Management