nerdexam
PMI

PMP · Question #177

An oil and gas project started without having acquired full funding for the project. The remaining funds were to be acquired during project execution. The acquisition of the remaining funds was delaye

The correct answer is B. Ensured the risk was adequately assessed and mitigated by the appropriate stakeholders.. To prevent project suspension due to delayed funding, the project manager should have ensured that the risk of funding acquisition was thoroughly assessed and appropriate mitigation strategies were in place.

Submitted by chiamaka_o· Apr 18, 2026Process

Question

An oil and gas project started without having acquired full funding for the project. The remaining funds were to be acquired during project execution. The acquisition of the remaining funds was delayed several months, resulting in a suspension of work by all contractors. What should the project manager have done to prevent this from happening?

Options

  • AEnsured the stakeholder anticipated obstacles to achieving financial closure on the remaining
  • BEnsured the risk was adequately assessed and mitigated by the appropriate stakeholders.
  • CEnsured the stakeholder who was providing additional funds remained interested in the project.
  • DEnsured the project team monitored and reviewed the project risk register periodically.

How the community answered

(45 responses)
  • A
    7% (3)
  • B
    78% (35)
  • C
    2% (1)
  • D
    13% (6)

Why each option

To prevent project suspension due to delayed funding, the project manager should have ensured that the risk of funding acquisition was thoroughly assessed and appropriate mitigation strategies were in place.

AEnsured the stakeholder anticipated obstacles to achieving financial closure on the remaining

While stakeholders should anticipate obstacles, the PM's role is more active; it's not just about anticipation but ensuring proactive assessment and mitigation of risks.

BEnsured the risk was adequately assessed and mitigated by the appropriate stakeholders.Correct

The scenario describes a known financial risk (remaining funds to be acquired during execution) that materialized due to inadequate assessment and mitigation. A project manager's responsibility is to proactively identify such risks, assess their likelihood and impact, and work with relevant stakeholders to develop and implement mitigation plans to prevent or reduce their occurrence.

CEnsured the stakeholder who was providing additional funds remained interested in the project.

Ensuring a stakeholder's interest is part of stakeholder management, but it doesn't directly address the financial closure process or the mechanisms to secure funds, which is the root of the problem.

DEnsured the project team monitored and reviewed the project risk register periodically.

Monitoring the risk register is an ongoing activity, but the failure here was in the initial assessment and mitigation of a known, significant risk before it caused project suspension.

Concept tested: Proactive risk management and mitigation

Source: https://docs.microsoft.com/en-us/azure/devops/boards/get-started/identify-track-risk-impediments

Topics

#Risk Management#Funding#Project Planning#Risk Mitigation

Community Discussion

6
Ingrid P.Ingrid P.Jul 1, 2026

B is correct because funding gaps are a classic project risk that should have been identified in the risk register, quantified, and assigned a mitigation strategy before execution started. Make a card on this: if a scenario describes a foreseeable external dependency causing work stoppage, the answer is always about proper risk assessment and mitigation by stakeholders, not after-the-fact monitoring.

23
Lena V.Lena V.Jul 1, 2026

Agree on the risk register angle but the exam usually wants the specific next step the PM takes when the gap actually hits mid-execution, which is submit a change request to adjust the budget or scope, not just retroactively point at the register.

0
Lena V.Lena V.Jul 5, 2026

B is the right call. D is tempting since the risk register should be reviewed, but the real failure happened upstream, during risk assessment and mitigation by stakeholders, not during monitoring.

4
Toby R.Toby R.Jul 5, 2026

Saw this one on my exam last month, almost talked myself into D because monitoring the risk register sounds responsible. But the stem is really asking what should have been done upfront to prevent the funding delay, which points to B, assessing and mitigating the risk with the right stakeholders before execution started.

4
Ingrid P.Ingrid P.Jul 7, 2026

B is correct and your reading of the stem as a prevention question rather than a response question is spot on, so if you make a card for this one tag it with risk management and not risk response so the interval spacing keeps it away from the monitor-and-control questions it gets confused with.

0
Brenda K.Brenda K.Jul 5, 2026

B is the quick win here, but would mitigation even fully prevent a funding delay?

4
Full PMP Practice