nerdexam
PMIPMI

PMP · Question #166

PMP Question #166: Real Exam Question with Answer & Explanation

Sign in or unlock PMP to reveal the answer and full explanation for question #166. The question stem and answer options stay visible for context.

Submitted by devops_kid· Apr 18, 2026Process

Question

A project is ready to start, and resources are allocated. The development manager then informs the project manager that a critical resource is no longer available due to a family emergency. The development manager indicates that all other developers have been assigned to other projects, and there is no capacity for any developer to take on additional work. What should the project manager do next to fulfill this resource need?

Options

  • ADetermine resource allocation options based on project priority.
  • BApply changes to the existing resource allocations and inform the development manager.
  • CMeet with the sponsor to determine how to rebaseline the schedule.
  • DInform the sponsor of the situation and request an extension of the target completion date.

Unlock PMP to see the answer

You've previewed enough free PMP questions. Unlock PMP for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.

Topics

#Resource Management#Resource Allocation#Project Prioritization#Issue Management
Full PMP PracticeBrowse All PMP Questions