During the sprint planning of a project, the team members have a disagreement about the comparative size of the backlog items and if they would fit into the next sprint. Considering a hybrid approach,

The correct answer is C. Facilitate the discussion so that the team members can reach a consensus.. As a facilitator in an agile or hybrid environment, the project manager should guide the team members through a discussion to help them achieve consensus on sizing backlog items and their fit for the sprint.

Submitted by yasin.bd· Apr 18, 2026People

Question

During the sprint planning of a project, the team members have a disagreement about the comparative size of the backlog items and if they would fit into the next sprint. Considering a hybrid approach, what should the project manager do?

Options

  • AAsk an external technical leader to provide input and plan the sprint.
  • BRemove the items from the product backlog since the size couldn't be estimated.
  • CFacilitate the discussion so that the team members can reach a consensus.
  • DMake the decision about the backlog items based on what makes more sense.

How the community answered

(47 responses)
  • A
    4% (2)
  • B
    2% (1)
  • C
    85% (40)
  • D
    9% (4)

Why each option

As a facilitator in an agile or hybrid environment, the project manager should guide the team members through a discussion to help them achieve consensus on sizing backlog items and their fit for the sprint.

AAsk an external technical leader to provide input and plan the sprint.

Bringing in an external technical leader without first allowing the team to attempt to resolve the disagreement internally undermines the team's self-organization and problem-solving abilities.

BRemove the items from the product backlog since the size couldn't be estimated.

Removing items from the backlog without team consensus or a thorough understanding of the reasons for disagreement is a premature and disruptive action that bypasses the planning process.

CFacilitate the discussion so that the team members can reach a consensus.Correct

In agile sprint planning, the project manager acts as a facilitator, empowering the self-organizing team to collaboratively discuss, estimate, and reach consensus on backlog item sizing and sprint commitments, fostering ownership and shared understanding.

DMake the decision about the backlog items based on what makes more sense.

Making the decision independently as the project manager, rather than facilitating the team to reach consensus, goes against agile principles of team self-organization and shared commitment.

Concept tested: Agile facilitation and team self-organization

Topics

#Sprint Planning#Conflict Resolution#Facilitation#Agile Leadership

Community Discussion

8
Fatima Z.Fatima Z.Jun 23, 2026

C is your winner. Think F.A.C.E.: Facilitate, Agree, Consensus, Empower. The PM in agile or hybrid is a servant-leader who guides the team to consensus, not a dictator who decides for them.

29
Brenda K.Brenda K.Jun 26, 2026

F.A.C.E. is a solid recall hook but watch your clock here because the servant-leader keyword in the stem makes this a 20-second pick, so bank the time for the earned value math questions later.

0
Brenda K.Brenda K.Jul 5, 2026

C is the quick win, the PM facilitates not decides. Does planning poker ring a bell here?

3
Yuki V.Yuki V.Jul 8, 2026

Yeah C is right, but planning poker is more of a sprint planning or estimating technique, not really the same as general facilitation where the PM just guides the discussion and lets the team own the decision.

0
Yusuf A.Yusuf A.Jun 6, 2026

Going with C. A is tempting because pulling in a senior tech lead sounds reasonable in a hybrid setup, but the PM's job is to facilitate, not hand off the decision, and D is wrong because the PM shouldn't be making the call for the team.

2
Fatima Z.Fatima Z.Jun 9, 2026

Spot on with C, Yusuf, and remember the handy filter PM-FACILITATES-NOT-DELEGATES to keep A from luring you in on exam day.

0
Samuel O.Samuel O.Jun 27, 2026

I first leaned toward D because in my experience someone has to break the stalemate and keep things moving. But the key word is facilitate, not decide - the PM clears the path so the team owns the sizing and the consensus, which is exactly what the exam wants.

2
Yuki V.Yuki V.Jun 18, 2026

Picked C on my exam last week. D is tempting because in a hybrid setup it feels like the PM should step in, but the PM facilitates the conversation rather than making the call for the team.

0