nerdexam
PMI

PMP · Question #160

When a project is in its final stage, the project manager will request from the team to prepare a delivery acceptance document. What is the importance of this document to the project manager?

The correct answer is C. Needed to close out the project or a phase.. The project manager requests a delivery acceptance document from the team in the final stage of a project.

Submitted by yuriko_h· Apr 18, 2026Process

Question

When a project is in its final stage, the project manager will request from the team to prepare a delivery acceptance document. What is the importance of this document to the project manager?

Options

  • ANeeded to close the work breakdown structure (WBS).
  • BNeeded to share it with the stakeholders.
  • CNeeded to close out the project or a phase.
  • DNeeded to release the team at the end of the project.

How the community answered

(33 responses)
  • B
    3% (1)
  • C
    94% (31)
  • D
    3% (1)

Why each option

The project manager requests a delivery acceptance document from the team in the final stage of a project.

ANeeded to close the work breakdown structure (WBS).

The Work Breakdown Structure (WBS) is a hierarchical decomposition of project work and is closed when all associated work packages are completed, not directly by a delivery acceptance document, although acceptance confirms the completion of those work packages.

BNeeded to share it with the stakeholders.

While the delivery acceptance document is shared with stakeholders, its primary importance to the project manager extends beyond mere sharing; it's a formal step for project closure and legal/contractual fulfillment.

CNeeded to close out the project or a phase.Correct

The delivery acceptance document formally confirms that the client or stakeholders have received and approved the project's deliverables, signifying that the project objectives have been met. This official acceptance is a critical prerequisite for formally closing out the project or a specific project phase, indicating that the work is complete and agreed upon by all parties.

DNeeded to release the team at the end of the project.

Releasing the team at the end of the project is a consequence of project completion and closure, which the acceptance document enables, but the document itself is not needed solely for the act of releasing the team; it's fundamental to the formal project closure process.

Concept tested: Project closure and formal acceptance

Topics

#Project Closure#Deliverable Acceptance#Formal Acceptance#Close Project or Phase

Community Discussion

5
Olusegun A.Olusegun A.Dec 31, 2025

C is correct. The delivery acceptance document is the formal confirmation from the customer or sponsor that the work meets requirements, which is the required input to close out the project or phase.

8
Bao N.Bao N.Jan 7, 2026

C is correct. Signed acceptance is the formal input to close the project or phase.

5
Olusegun A.Olusegun A.Jan 9, 2026

Agreed on C, but remember the accepted deliverables come from the Validate Scope process, which is where you actually get that signoff before Close Project or Phase consumes it as an input.

0
Ingrid P.Ingrid P.Jan 22, 2026

I am going with D here. The delivery acceptance document is the trigger that lets the PM formally release the team, because until the customer signs off on acceptance, the team is still on the hook for the work. Without that signed acceptance, you cannot cleanly disband resources or close out their charge codes. I just made a flashcard on this: final stage delivery acceptance document equals formal release of team. If anyone has seen this one on the exam, chime in.

0
Olusegun A.Olusegun A.Jan 23, 2026

C is correct, Ingrid. The final report is what gets produced at project end to capture lessons learned and performance summary, not a delivery acceptance document, which is really just the verified deliverable input that happens earlier in the closeout process.

0
Full PMP Practice