A project team has established contracts for purchasing vehicles and construction services. In the middle of project execution, the team learns that the vehicle supplier cannot deliver the vehicles. T

The correct answer is C. Review the existing service contracts to find an option to help procure the vehicles.. A critical vehicle supplier cannot deliver, and there isn't enough time to find a new supplier without delaying the project.

Submitted by obi.ng· Apr 18, 2026Process

Question

A project team has established contracts for purchasing vehicles and construction services. In the middle of project execution, the team learns that the vehicle supplier cannot deliver the vehicles. There is not enough time to find a new supplier without delaying the project. Which action should the project manager take to procure the vehicles?

Options

  • AAsk the technical team to revise the requirements, even if it requires extra budget.
  • BArrange a meeting with the client to request additional time to find a new supplier.
  • CReview the existing service contracts to find an option to help procure the vehicles.
  • DProcure the vehicles from another supplier and report the change to the change control board

How the community answered

(25 responses)
  • A
    8% (2)
  • B
    12% (3)
  • C
    48% (12)
  • D
    32% (8)

Why each option

A critical vehicle supplier cannot deliver, and there isn't enough time to find a new supplier without delaying the project.

AAsk the technical team to revise the requirements, even if it requires extra budget.

Asking the technical team to revise requirements might be an option if no vehicles can be procured, but it's a significant scope change that should be a later resort, as the immediate need is to procure the vehicles as originally planned if possible.

BArrange a meeting with the client to request additional time to find a new supplier.

Arranging a meeting with the client to request more time is an option if no internal solutions are found, but it represents an acceptance of delay rather than an attempt to find an immediate solution to maintain the schedule.

CReview the existing service contracts to find an option to help procure the vehicles.Correct

When a primary supplier fails, a proactive project manager should first explore existing resources and agreements. Reviewing other established service contracts for construction might reveal clauses, partnerships, or procurement capabilities that could be leveraged to quickly acquire the necessary vehicles or an equivalent solution, potentially mitigating the delay and avoiding new, time-consuming procurement processes.

DProcure the vehicles from another supplier and report the change to the change control board

Procuring from another supplier directly without a clear alternative identified, especially under time pressure, is risky and might not be feasible without delay. Also, reporting to the change control board after procurement is not ideal; the priority is finding a quick, compliant solution first, then managing the change.

Concept tested: Procurement issue resolution and resource leveraging

Topics

#Procurement Management#Contract Management#Supplier Management#Issue Resolution

Community Discussion

3
Mei-Ling H.Mei-Ling H.Dec 29, 2025

C is correct. The key qualifier in the stem is that there is "not enough time to find a new supplier," which immediately eliminates option D. The question deliberately mentions the established construction service contracts because the project manager should review them first to see if a clause or existing vendor relationship can help procure the vehicles. Option B is a trap because asking the client for more time contradicts the urgency constraint, and option A unnecessarily changes scope. On my exam last month, this type of "use what you already have" scenario showed up twice.

19
Orla P.Orla P.Jan 13, 2026

Saw this one on my exam last month and picked C because the other three either burn schedule or skip process. The key is the question mentions the service contracts for a reason, you leverage what you already have in place before going outside the box.

5
Luis F.Luis F.Jan 21, 2026

C is right. Existing service contracts might already cover vehicle procurement.