PMP · Question #161

PMP Question #161: Real Exam Question with Answer & Explanation

Sign in or unlock PMP to reveal the answer and full explanation for question #161. The question stem and answer options stay visible for context.

Submitted by certguy· Apr 18, 2026People

Question

A project manager is leading a project that has a dependency on the client's vendor management system for critical requirements. The vendor management team will not derive any benefits from the project. However, the project requires support from the vendor management head. What should the project manager do next?

Options

  • AGet support from the sponsor to hire a subject matter expert (SME) from the vendor management
  • BReview the terms of reference of the steering committee to include the vendor management
  • CWork with the sponsor on a communications management plan to obtain support from the vendor
  • DObtain help from the sponsor to highlight any nonfinancial benefits for the vendor management

Unlock PMP to see the answer

You've previewed enough free PMP questions. Unlock PMP for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.

Topics

#Stakeholder Engagement#Project Governance#Steering Committee#Stakeholder Influence