PMP · Question #162

PMP Question #162: Real Exam Question with Answer & Explanation

Sign in or unlock PMP to reveal the answer and full explanation for question #162. The question stem and answer options stay visible for context.

Submitted by amina.ke· Apr 18, 2026People

Question

A subject matter expert (SME) external to the project team provides a suggestion that will save the project delivery time. This SME has available time to support the project, but was not planned to be involved in the current agile iteration. What should the project manager do?

Options

  • ABring the SME on board immediately and discuss the implications later.
  • BAsk the existing team members to collaborate with the SME and complete the activity.
  • CAsk the SME to complete all of the necessary changes, which will save time.
  • DDirect the team member to ignore the SME's changes as they were not planned.

Unlock PMP to see the answer

You've previewed enough free PMP questions. Unlock PMP for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.

Topics

#Agile methodologies#Stakeholder engagement#Team collaboration#Adaptability
Full PMP PracticeBrowse All PMP Questions