A project manager is leading a global project with resources spread out in different locations. The stakeholders have different interpretations of the requirements. The project manager is concerned about scope creep. Which action should the project manager take to control the scope?

Options

  • AEnsure that all key stakeholders agree to the project deliverables and there will be no need for
  • BAccept only those changes to requirements that provide additional value to the project.
  • CReject all changes that will increase the budget or increase the time line of the project.
  • DAccept only those changes that are approved by the change control board (CCB) prior to being

Unlock PMP to see the answer

You've previewed enough free PMP questions. Unlock PMP for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.

Topics

#Scope Control#Change Control Board#Change Management
Full PMP PracticeBrowse All PMP Questions