PMIPMI
PMP · Question #151
PMP Question #151: Real Exam Question with Answer & Explanation
Sign in or unlock PMP to reveal the answer and full explanation for question #151. The question stem and answer options stay visible for context.
Submitted by yousef_jo· Apr 18, 2026Process
Question
A project manager is leading a global project with resources spread out in different locations. The stakeholders have different interpretations of the requirements. The project manager is concerned about scope creep. Which action should the project manager take to control the scope?
Options
- AEnsure that all key stakeholders agree to the project deliverables and there will be no need for
- BAccept only those changes to requirements that provide additional value to the project.
- CReject all changes that will increase the budget or increase the time line of the project.
- DAccept only those changes that are approved by the change control board (CCB) prior to being
Unlock PMP to see the answer
You've previewed enough free PMP questions. Unlock PMP for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.
Topics
#Scope Control#Change Control Board#Change Management