PMP · Question #152
PMP Question #152: Real Exam Question with Answer & Explanation
Sign in or unlock PMP to reveal the answer and full explanation for question #152. The question stem and answer options stay visible for context.
Question
During a kick-off meeting, the project manager notices that one of the stakeholders responsible for providing key information to the team has a low level of participation. This stakeholder believes that there will be no benefit from implementing the project. The project manager realizes that this could be a high risk for the project. Which action should the project manager take?
Options
- AFacilitate a supportive level of engagement for this stakeholder.
- BAsk the project sponsor for advice as it might be possible to work with another stakeholder.
- CPerform a qualitative risk analysis using a probability and impact matrix.
- DEnsure the key information is accurate and monitor the situation as the project progresses.
Unlock PMP to see the answer
You've previewed enough free PMP questions. Unlock PMP for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.