PMP · Question #150

PMP Question #150: Real Exam Question with Answer & Explanation

Sign in or unlock PMP to reveal the answer and full explanation for question #150. The question stem and answer options stay visible for context.

Submitted by carter_n· Apr 18, 2026People

Question

A team shared a complaint regarding the scrum master during the last sprint review. The team expressed that they were delayed because the scrum master did not remove impediments, such as scheduling some meetings with external teams and obtaining a room to work collaboratively, among other critical blockers. What should the project manager do?

Options

  • ARequest an additional resource to assist in solving all of the impediments listed by the team.
  • BDetermine and agree when a situation becomes an impediment to be solved by the scrum
  • CRequest the team review and prioritize the open impediments to resolve all of them as soon as
  • DPush back, explaining that a self-organized team should address all of the problems to get the

Unlock PMP to see the answer

You've previewed enough free PMP questions. Unlock PMP for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.

Topics

#Scrum Master role#Impediment resolution#Team accountability#Expectation setting
Full PMP PracticeBrowse All PMP Questions