PMP · Question #149

PMP Question #149: Real Exam Question with Answer & Explanation

Sign in or unlock PMP to reveal the answer and full explanation for question #149. The question stem and answer options stay visible for context.

Submitted by omar99· Apr 18, 2026People

Question

A mid-size capital project has shared resources from the company's contract department. During the execution phase, the project team observed a delay in contracting. After communicating with the contract department, the project manager found the contract team is prioritizing other contracting jobs because they are not part of the project team. What should the project manager do first in this situation?

Options

  • AReport the issue to higher management and seek their direct involvement to complete the job
  • BArrange a meeting with the contract department to build trust and commitment by recognizing
  • CArrange several meetings with the contract department and ask them to contract the project as it
  • DCommunicate with the contract manager to commit a budget for the resources required for project

Unlock PMP to see the answer

You've previewed enough free PMP questions. Unlock PMP for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.

Topics

#Stakeholder engagement#Conflict resolution#Shared resources management#Team commitment