Question
A project manager has been assigned to a new digital product line, which the company hopes will boost their revenue. The product is complex and requires customer feedback to continually refine the product. The project is being handled by a cross-functional agile team. What should the project manager do to ensure value is delivered quickly?
Options
- AAsk the project sponsor to provide additional resources to fast track the project
- BPlan the project to deliver value incrementally with regular releases
- CRequest a budget increase to pay the subject matter experts (SMEs) more overtime
- DIdentify tasks that can run in parallel to deliver the project faster