nerdexam
PMIPMI

PMP · Question #1395

PMP Question #1395: Real Exam Question with Answer & Explanation

Sign in or unlock PMP to reveal the answer and full explanation for question #1395. The question stem and answer options stay visible for context.

Submitted by fatema_kw· Apr 18, 2026Process

Question

A project manager has been assigned to a new digital product line, which the company hopes will boost their revenue. The product is complex and requires customer feedback to continually refine the product. The project is being handled by a cross-functional agile team. What should the project manager do to ensure value is delivered quickly?

Options

  • AAsk the project sponsor to provide additional resources to fast track the project
  • BPlan the project to deliver value incrementally with regular releases
  • CRequest a budget increase to pay the subject matter experts (SMEs) more overtime
  • DIdentify tasks that can run in parallel to deliver the project faster

Unlock PMP to see the answer

You've previewed enough free PMP questions. Unlock PMP for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.

Topics

#Agile principles#Incremental delivery#Value delivery#Release planning
Full PMP PracticeBrowse All PMP Questions