nerdexam
PMI

PMP · Question #1397

A project is designed to provide local community members with health facilities that will support improved sanitation practices. What should the project manager do to ensure the community members…

The correct answer is C. Share project updates through regular community meetings. To keep community members updated on the progress of health facilities, the project manager should share project updates through regular community meetings.

Submitted by zhang_li· Apr 18, 2026People

Question

A project is designed to provide local community members with health facilities that will support improved sanitation practices. What should the project manager do to ensure the community members are up to date on project progress?

Options

  • AShare the annual reports virtually and in the local newspapers
  • BShare project updates when requested by the stakeholders
  • CShare project updates through regular community meetings
  • DShare the project reports with the sponsor to inform community members

How the community answered

(31 responses)
  • A
    3% (1)
  • B
    6% (2)
  • C
    77% (24)
  • D
    13% (4)

Why each option

To keep community members updated on the progress of health facilities, the project manager should share project updates through regular community meetings.

AShare the annual reports virtually and in the local newspapers

Sharing annual reports and using local newspapers may be too infrequent or broad for detailed, ongoing project progress, and may not reach all community members effectively or allow for direct interaction.

BShare project updates when requested by the stakeholders

Only sharing updates when requested is a reactive approach and does not fulfill the proactive responsibility of keeping key stakeholders, like community members, regularly informed about a project that directly benefits them.

CShare project updates through regular community meetingsCorrect

For a project directly impacting a local community, sharing updates through regular community meetings is the most effective and appropriate method. This allows for direct, two-way communication, enabling community members to ask questions, provide feedback, and stay informed in a transparent and inclusive manner.

DShare the project reports with the sponsor to inform community members

Sharing reports with the sponsor to inform community members is an indirect communication channel; the project manager should engage directly with the primary stakeholders who are the community members themselves.

Concept tested: Stakeholder communication, community engagement, communication methods

Source: https://www.pmi.org/pmbok-guide-standards/foundational/pmbok

Topics

#Stakeholder Engagement#Communication Management#Community Relations#Project Communication

Community Discussion

3
Hiroshi T.Hiroshi T.Jul 5, 2026

C is correct. PMI emphasizes proactive stakeholder engagement, and for a local community project, regular community meetings ensure timely two-way communication rather than waiting for requests or routing updates through the sponsor.

23
Prof. SaraProf. SaraJun 22, 2026

C is correct. I quibble with the wording because "up to date" implies a push strategy, yet C only works if those meetings are actually frequent enough. A is tempting because it covers virtual and print, but annual reports are far too sparse for a sanitation project and likely miss stakeholders without internet access. Remember the Stakeholder Engagement domain: local community = high interest, so regular face-to-face meetings are the standard PMI answer.

3
Anjali D.Anjali D.Jul 1, 2026

Our group agrees on C. Regular community meetings fit best for local engagement.

0
Full PMP Practice