nerdexam
PMI

PMP · Question #1398

A project manager is assigned to a major system integration project that is currently in the execution phase. The project relies heavily on the presence and availability of certain products and servic

Sign in or unlock PMP to reveal the answer and full explanation for question #1398. The question stem and answer options stay visible for context.

Submitted by fatima_kr· Apr 18, 2026Process

Question

A project manager is assigned to a major system integration project that is currently in the execution phase. The project relies heavily on the presence and availability of certain products and services, which are provided at various periods throughout the project phases by selected third-party vendors. What should the project manager do to ensure the successful execution of the project?

Options

  • AOversee the selection process for the vendor to procure the needed products and services.
  • BAsk the procurement department to select the vendor using established processes.
  • CActivate the mitigation plan for the procurement risks.
  • DPerform procurement control checks throughout the project.

Unlock PMP to see the answer

You've previewed enough free PMP questions. Unlock PMP for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.

Topics

#Procurement Management#Control Procurements#Vendor Management#Project Execution
Full PMP Practice