PMP · Question #1394
A company that is introducing a new product into the market by the end of the year requires a storage and distribution facility to be built. During the monthly stakeholder meeting, it is discovered…
The correct answer is A. Update the risk register. Upon discovering that a planned facility location is on government-owned land, the project manager should first update the risk register.
Question
Options
- AUpdate the risk register
- BUpdate the issue log
- CIdentify an alternative site
- DIssue a change request
How the community answered
(47 responses)- A83% (39)
- B6% (3)
- C2% (1)
- D9% (4)
Why each option
Upon discovering that a planned facility location is on government-owned land, the project manager should first update the risk register.
Discovering that the chosen location is government-owned introduces a new uncertainty or potential problem for the project. Before taking any other action, this situation must be formally identified, assessed for its probability and impact, and documented in the risk register as a new risk.
The issue log is for problems that have already occurred or are actively happening; at this stage, the government ownership is a potential problem (risk), not a confirmed issue disrupting the project.
Identifying an alternative site is a potential response to the risk, but it should only be pursued after the risk has been properly identified, analyzed, and documented, to ensure the response is appropriate.
Issuing a change request is a formal process to modify project baselines and requires a clear understanding of the proposed change and its implications, which comes after risk assessment and response planning.
Concept tested: Risk identification, risk register maintenance
Source: https://www.pmi.org/pmbok-guide-standards/foundational/pmbok
Topics
Community Discussion
No community discussion yet for this question.