nerdexam
PMI

PMP · Question #1394

A company that is introducing a new product into the market by the end of the year requires a storage and distribution facility to be built. During the monthly stakeholder meeting, it is discovered…

The correct answer is A. Update the risk register. Upon discovering that a planned facility location is on government-owned land, the project manager should first update the risk register.

Submitted by dimitri_ru· Apr 18, 2026Process

Question

A company that is introducing a new product into the market by the end of the year requires a storage and distribution facility to be built. During the monthly stakeholder meeting, it is discovered that the location for implementation is a government-owned area. What should the project manager do first?

Options

  • AUpdate the risk register
  • BUpdate the issue log
  • CIdentify an alternative site
  • DIssue a change request

How the community answered

(47 responses)
  • A
    83% (39)
  • B
    6% (3)
  • C
    2% (1)
  • D
    9% (4)

Why each option

Upon discovering that a planned facility location is on government-owned land, the project manager should first update the risk register.

AUpdate the risk registerCorrect

Discovering that the chosen location is government-owned introduces a new uncertainty or potential problem for the project. Before taking any other action, this situation must be formally identified, assessed for its probability and impact, and documented in the risk register as a new risk.

BUpdate the issue log

The issue log is for problems that have already occurred or are actively happening; at this stage, the government ownership is a potential problem (risk), not a confirmed issue disrupting the project.

CIdentify an alternative site

Identifying an alternative site is a potential response to the risk, but it should only be pursued after the risk has been properly identified, analyzed, and documented, to ensure the response is appropriate.

DIssue a change request

Issuing a change request is a formal process to modify project baselines and requires a clear understanding of the proposed change and its implications, which comes after risk assessment and response planning.

Concept tested: Risk identification, risk register maintenance

Source: https://www.pmi.org/pmbok-guide-standards/foundational/pmbok

Topics

#Risk Management#Risk Identification#Risk Register

Community Discussion

No community discussion yet for this question.

Full PMP Practice