PMP · Question #1358
PMP Question #1358: Real Exam Question with Answer & Explanation
Sign in or unlock PMP to reveal the answer and full explanation for question #1358. The question stem and answer options stay visible for context.
Question
A project manager is working on a project to build a manufacturing complex. The project will run in three different phases: engineering, procurement, and construction. The procurement phase is in the initiation stage. The project sponsor wants to pursue the project phases as they have been planned, but also wants to accommodate and adjust to new data, input from the customer, and changes during the various phases as the project progresses. How should the project manager approach this project?
Options
- AUse a hybrid model to combine predictive and adaptive life cycles.
- BImplement an adaptive project management approach.
- CEvaluate and decide on a phased project management approach.
- DApply a predictive project management approach.
Unlock PMP to see the answer
You've previewed enough free PMP questions. Unlock PMP for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.