PMP · Question #1360

PMP Question #1360: Real Exam Question with Answer & Explanation

Sign in or unlock PMP to reveal the answer and full explanation for question #1360. The question stem and answer options stay visible for context.

Submitted by minji_kr· Apr 18, 2026Process

Question

An organization is transitioning to an agile approach. At the project's first sprint review, the product owner did not accept the result of the sprint and has some concerns. What should the project manager do?

Options

  • AAsk the project team to address the product owner's issues since the product owner is
  • BCreate a record in the issue register and escalate the issue to the project steering committee.
  • CAsk the product owner to accept the outcome since the team delivered what was agreed in the
  • DOrganize a sprint retrospective and discuss the issues and how they can be avoided in the next

Unlock PMP to see the answer

You've previewed enough free PMP questions. Unlock PMP for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.

Topics

#Agile Ceremonies#Sprint Retrospective#Product Owner#Continuous Improvement