PMIPMI
PMP · Question #13
PMP Question #13: Real Exam Question with Answer & Explanation
Sign in or unlock PMP to reveal the answer and full explanation for question #13. The question stem and answer options stay visible for context.
Submitted by priya_blr· Apr 18, 2026Process
Question
During a system demo, a project stakeholder rejects the features completed from the most recent user stories. According to the stakeholder, the product does not meet the quality standards required by regulations. What should the project manager have done to avoid this?
Options
- AEnsured that the project sponsor understood the scope of the project to avoid any future
- BEnsured the stakeholder concerns were properly addressed in the iteration to avoid future
- CReviewed with the product owner that all acceptance criteria were met for the stories worked on
- DReviewed with the product owner that all the stories worked on in the iteration were in the project
Unlock PMP to see the answer
You've previewed enough free PMP questions. Unlock PMP for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.
Topics
#Stakeholder engagement#Quality management#Requirements management#Risk prevention