PMIPMI
PMP · Question #14
PMP Question #14: Real Exam Question with Answer & Explanation
Sign in or unlock PMP to reveal the answer and full explanation for question #14. The question stem and answer options stay visible for context.
Submitted by thandi_sa· Apr 18, 2026Process
Question
A project is 70% complete when the project sponsor requests an additional deliverable. What should the project manager do first?
Options
- ANegotiate with the project sponsor on the possible alternatives
- BDetermine the possible impact of this change on all aspects of the project
- CReject the request as being too late and leading to major scope creep
- DSubmit the request to the change control board (CCB) for a decision
Unlock PMP to see the answer
You've previewed enough free PMP questions. Unlock PMP for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.
Topics
#Change Management#Scope Management#Integrated Change Control#Impact Analysis