PMIPMI
PMP · Question #1261
PMP Question #1261: Real Exam Question with Answer & Explanation
Sign in or unlock PMP to reveal the answer and full explanation for question #1261. The question stem and answer options stay visible for context.
Submitted by dimitri_ru· Apr 18, 2026Process
Question
A project manager created a contingency plan associated with a risk. The risk was realized, but the client insists on using a new workaround instead. The requested workaround will introduce delays and require additional budget. What should the project manager do?
Options
- ARequest to use the management reserve to keep the schedule.
- BDiscuss the options with the client as part of the change control process.
- CProceed with the approved risk response plan.
- DMitigate risks associated with the workaround to avoid project delays.
Unlock PMP to see the answer
You've previewed enough free PMP questions. Unlock PMP for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.
Topics
#Risk Management#Change Control#Stakeholder Management#Client Communication