PMP · Question #1262

PMP Question #1262: Real Exam Question with Answer & Explanation

Sign in or unlock PMP to reveal the answer and full explanation for question #1262. The question stem and answer options stay visible for context.

Submitted by ashley.k· Apr 18, 2026People

Question

A project manager is leading three projects in a program focused on starting product commercialization. Once the three projects start going to market, the project manager stops attending the recurring team meetings. The program manager asks the project manager to continue attending these meetings to maintain those team touchpoints. This request does not match the project manager's expectation, since a program manager is overseeing the remaining work. How should the project manager approach the situation?

Options

  • ASchedule a meeting to discuss the different perspectives and agree on a decision.
  • BPolitely inform the program manager that attending these meetings is no longer required.
  • CProvide an answer via email recommending a division of tasks between both roles.
  • DAttend only the program meetings where the market launch is being monitored.

Unlock PMP to see the answer

You've previewed enough free PMP questions. Unlock PMP for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.

Topics

#Stakeholder Management#Communication#Conflict Resolution#Roles and Responsibilities