PMIPMI
PMP · Question #1259
PMP Question #1259: Real Exam Question with Answer & Explanation
Sign in or unlock PMP to reveal the answer and full explanation for question #1259. The question stem and answer options stay visible for context.
Submitted by fernanda_arg· Apr 18, 2026Process
Question
A project manager is assigned to a project with a long time line and complex scope. The client requires a high-level, long-term plan as well as something that will work immediately, adding features to the product as the project progresses. How should the project manager plan and deliver this project?
Options
- APlan the project with a predictive approach with a work breakdown structure (WBS) and then
- BPlan the project with a predictive approach and a work breakdown structure (WBS) following the
- CAgree on a minimum viable product (MVP) first to be delivered immediately with the client and
- DSelect an agile approach and manage the project according to best practices to ensure value is
Unlock PMP to see the answer
You've previewed enough free PMP questions. Unlock PMP for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.
Topics
#Hybrid Project Management#Project Life Cycles#Planning Approaches#Adaptive vs. Predictive