nerdexam
PMIPMI

PMP · Question #1258

PMP Question #1258: Real Exam Question with Answer & Explanation

Sign in or unlock PMP to reveal the answer and full explanation for question #1258. The question stem and answer options stay visible for context.

Submitted by stefanr· Apr 18, 2026Business Environment

Question

A project manager works for a company that has a reputation of delivering environmentally sustainable projects. During the half- yearly review of the project, the project manager raises serious concerns with the project sponsor regarding the project's viability and success. There are some stakeholders who oppose this project on the grounds of compromising land erosion. What should the project manager do?

Options

  • ARequest additional resources from the business unit manager due to the project's complexity.
  • BCalculate float on the project because it has severely affected the project's major critical path.
  • CPropose to close the project because it no longer fits the business values of the organization.
  • DCalculate earned value (EV) because the project manager is forecasting a loss for this project in

Unlock PMP to see the answer

You've previewed enough free PMP questions. Unlock PMP for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.

Topics

#Strategic Alignment#Organizational Values#Stakeholder Engagement#Project Closure
Full PMP PracticeBrowse All PMP Questions