nerdexam
PMIPMI

PMP · Question #1240

PMP Question #1240: Real Exam Question with Answer & Explanation

Sign in or unlock PMP to reveal the answer and full explanation for question #1240. The question stem and answer options stay visible for context.

Submitted by layla.eg· Apr 18, 2026Process

Question

A risk was identified at the beginning of a project, and a response plan was established. Unforeseen consequences resulted in a higher level of risk. The project manager has an idea that could address the new risk in an efficient way, but the response is different from the original risk mitigation plan. What should the project manager do?

Options

  • ASubmit the new response plan to the stakeholders for their review.
  • BObtain management approval prior to implementing the new risk response.
  • CImplement the new response to address the risk.
  • DUse the management reserve to mitigate the risk.

Unlock PMP to see the answer

You've previewed enough free PMP questions. Unlock PMP for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.

Topics

#Risk Management#Stakeholder Engagement#Project Governance#Change Management
Full PMP PracticeBrowse All PMP Questions