PMIPMI
PMP · Question #1210
PMP Question #1210: Real Exam Question with Answer & Explanation
Sign in or unlock PMP to reveal the answer and full explanation for question #1210. The question stem and answer options stay visible for context.
Submitted by lars.no· Apr 18, 2026Process
Question
An organization is transitioning to agile. The project manager is discussing how to manage risks with the development team in light of the transition for a particular project. The team estimates the risk level as low. What should the project manager do?
Options
- ACreate a risk register to identify, capture, review, and manage risks using a risk management
- BTrust the development team's risk estimation and inform the project sponsor that the risks will be
- CCreate a risk register and include a single generic risk, set the level to low, and then close the risk
- DCapture all the backlog entries assessed by the development team to have evidence that risk
Unlock PMP to see the answer
You've previewed enough free PMP questions. Unlock PMP for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.
Topics
#Risk Management#Agile Practices#Project Manager Responsibilities#Risk Register