PMI
PMP · Question #1209
A system migration project is in its closing stage. The project manager is being pressured to close the project. The project manager communicated to all stakeholders; however, the last department to m
Sign in or unlock PMP to reveal the answer and full explanation for question #1209. The question stem and answer options stay visible for context.
Submitted by kavita_s· Apr 18, 2026Process
Question
A system migration project is in its closing stage. The project manager is being pressured to close the project. The project manager communicated to all stakeholders; however, the last department to migrate indicated that they have not received the notification. What should the project manager do?
Options
- AClose out the project and tell the manager to open a service desk ticket.
- BLog the issue and assign it to the project team member(s).
- CEscalate the issue to the project sponsor and upper management.
- DReport the issue during the next status meeting at the end of the week.
Unlock PMP to see the answer
You've previewed enough free PMP questions. Unlock PMP for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.
Topics
#Project Closure#Issue Management#Communication Management#Scope Completion