PMP · Question #1183
PMP Question #1183: Real Exam Question with Answer & Explanation
Sign in or unlock PMP to reveal the answer and full explanation for question #1183. The question stem and answer options stay visible for context.
Question
A project manager is managing a project for a government owned company using an iterative approach. The first useful release to production consisted of three iterations. Each iteration was successfully checked by the client's representatives in the test environment. However, when the team started deploying to the production environment, the security team declined it. What should the project manager have done to prevent this?
Options
- AImplemented the authorization in the first iteration
- BReviewed the compliance requirements with stakeholders
- CDeployed to production after the first iteration
- DPlanned smaller iterations to review the results more often
Unlock PMP to see the answer
You've previewed enough free PMP questions. Unlock PMP for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.