nerdexam
PMIPMI

PMP · Question #1172

PMP Question #1172: Real Exam Question with Answer & Explanation

Sign in or unlock PMP to reveal the answer and full explanation for question #1172. The question stem and answer options stay visible for context.

Submitted by manish99· Apr 18, 2026Process

Question

In an advanced stage of a project, a stakeholder who is not receiving the project status report communicates this to the project manager. After checking, the project manager determines that the person is registered as a stakeholder but was not included in the communications management plan. What should the project manager do next?

Options

  • AUpdate the communications management plan to include the missed stakeholder, and send the
  • BAsk the stakeholder to get the project status report from another stakeholder listed in the
  • CInform the project sponsor that there are stakeholders who are not included in the
  • DInform the stakeholder that the project team cannot provide information to anyone who is not

Unlock PMP to see the answer

You've previewed enough free PMP questions. Unlock PMP for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.

Topics

#Stakeholder management#Communications management#Communications management plan#Project document updates
Full PMP PracticeBrowse All PMP Questions