nerdexam
PMI

PMP · Question #1171

A project manager who works for a company involved in several industries is asked to lead a software development project for a government agency. The company attempted to execute similar projects for

The correct answer is B. Review the lessons learned registers from the previous projects.. When taking on a project similar to past unsuccessful ventures, the project manager should review prior lessons learned to identify pitfalls and best practices.

Submitted by kim_seoul· Apr 18, 2026Process

Question

A project manager who works for a company involved in several industries is asked to lead a software development project for a government agency. The company attempted to execute similar projects for other industries before but was unsuccessful. What should the project manager do to ensure project success?

Options

  • AContinue executing the project using expert judgment.
  • BReview the lessons learned registers from the previous projects.
  • CDocument this information in the risk management plan.
  • DDevelop a contingency plan to prepare for possible risks.

How the community answered

(22 responses)
  • A
    9% (2)
  • B
    86% (19)
  • C
    5% (1)

Why each option

When taking on a project similar to past unsuccessful ventures, the project manager should review prior lessons learned to identify pitfalls and best practices.

AContinue executing the project using expert judgment.

Continuing execution solely based on expert judgment, without analyzing past failures, is a risky approach and ignores valuable historical data.

BReview the lessons learned registers from the previous projects.Correct

Reviewing lessons learned registers from previous, similar unsuccessful projects is crucial to identify root causes of failure, understand what went wrong, and incorporate those insights to avoid repeating mistakes and improve the current project's chances of success.

CDocument this information in the risk management plan.

Documenting this information in the risk management plan is a subsequent step, but the first action is to gather and analyze the information from past failures.

DDevelop a contingency plan to prepare for possible risks.

Developing a contingency plan is part of risk response planning, which comes after identifying and analyzing risks, including those uncovered by lessons learned.

Concept tested: Organizational Process Assets (OPA) and lessons learned

Topics

#Lessons Learned#Historical Information#Project Success Factors#Organizational Process Assets

Community Discussion

5
Samuel O.Samuel O.Oct 27, 2025

B is the move here. In my experience those lessons learned registers are gold, especially when the company has a track record of faceplanting on similar work, so you dig into what went wrong before you repeat it.

30
Orla P.Orla P.Oct 13, 2025

B is correct here. Since the company already tried similar projects and failed, the lessons learned register is exactly where you find out what went wrong so you do not repeat those mistakes.

4
Luis F.Luis F.Oct 15, 2025

Agreed on B, and just to add, the lessons learned register is also an input you would actually update during this project so you are capturing new lessons as you go, not just reading old ones.

0
Luis F.Luis F.Oct 20, 2025

Going with C here. The company has a track record of failing on similar projects, so documenting that historical failure pattern in the risk management plan is exactly what you do before anything else, it makes sure the team is aware of the risk from day one.

0
Orla P.Orla P.Oct 23, 2025

B is correct here. The scenario is asking you to identify the specific risk, which lands in the risk register, not the risk management plan. The risk management plan describes your methodology and process for handling risks overall, while the register is where you log the actual identified risks like this company's history of project failures.

0
Full PMP Practice