nerdexam
PMIPMI

PMP · Question #1162

PMP Question #1162: Real Exam Question with Answer & Explanation

Sign in or unlock PMP to reveal the answer and full explanation for question #1162. The question stem and answer options stay visible for context.

Submitted by fatema_kw· Apr 18, 2026Process

Question

A project manager is in the middle or handling a major upgrade to an existing product. The project manager learns that the resources initially promised as part or the project are being moved to another priority project. What should the project manager do?

Options

  • APerform an impact analysis to see the effect on the project
  • BExamine ways of modifying the scope of the project.
  • CAdopt a resource leveling procedure to level the resources
  • DRetrieve the documentation that shows the resource allocation

Unlock PMP to see the answer

You've previewed enough free PMP questions. Unlock PMP for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.

Topics

#Resource Management#Change Management#Impact Analysis#Problem Solving
Full PMP PracticeBrowse All PMP Questions