nerdexam
PMIPMI

PMP · Question #1161

PMP Question #1161: Real Exam Question with Answer & Explanation

Sign in or unlock PMP to reveal the answer and full explanation for question #1161. The question stem and answer options stay visible for context.

Submitted by andres_qro· Apr 18, 2026People

Question

One of the key stakeholders on the project team reaches out with an additional requirement that may impact the overall schedule. A discussion with another stakeholder suggests that this might just be a small task. What should the project manager do?

Options

  • APerform a qualitative risk analysis.
  • BCoordinate design document preparation.
  • CRequest further clarification of the requirement.
  • DManage the engagement of this stakeholder.

Unlock PMP to see the answer

You've previewed enough free PMP questions. Unlock PMP for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.

Topics

#Requirements clarification#Stakeholder communication#Information gathering#Scope management
Full PMP PracticeBrowse All PMP Questions