nerdexam
PMIPMI

PMP · Question #1147

PMP Question #1147: Real Exam Question with Answer & Explanation

Sign in or unlock PMP to reveal the answer and full explanation for question #1147. The question stem and answer options stay visible for context.

Submitted by klara.se· Apr 18, 2026Process

Question

A project is starting its third iteration out of six. During planning, the team realized that all of the requirements were not defined clearly enough to start working. What should the project manager do?

Options

  • AReview and replace the unclear requirements with ones that are clear.
  • BUpdate the issue log and escalate it to the project sponsor.
  • CMeet with the product owner to review the project backlog.
  • DInvite key users to the next daily meeting to get requirement clarification.

Unlock PMP to see the answer

You've previewed enough free PMP questions. Unlock PMP for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.

Topics

#Agile methodologies#Requirements clarification#Product Owner role#Backlog refinement
Full PMP PracticeBrowse All PMP Questions