nerdexam
PMIPMI

PMP · Question #11

PMP Question #11: Real Exam Question with Answer & Explanation

Sign in or unlock PMP to reveal the answer and full explanation for question #11. The question stem and answer options stay visible for context.

Submitted by brentm· Apr 18, 2026Process

Question

A project manager has been given a critical, 5-day window and is allocated a maximum of US$100,000 as a contingency reserve. Subsequently, the project manager drafted a course of action based upon the best available information. Overall, five actions were required to be completed at a cost of US$20,000 and a duration of 1 day each. After 3 days of work, the project manager completed two actions and spent US$80,000. What should the project manager do next?

Options

  • AComplete all actions and then inform the client of the additional cost and schedule overrun
  • BStop the work and raise a project change request to the change control board (CCB) for
  • CAs the CPI and SPI are greater than 1.0, reevaluate and prioritize the remaining actions
  • DAs the cost performance index (CPI) and schedule performance index (SPI) are less than 1.0,

Unlock PMP to see the answer

You've previewed enough free PMP questions. Unlock PMP for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.

Topics

#Earned Value Management#Variance Analysis#Constraint Management#Stakeholder Communication
Full PMP PracticeBrowse All PMP Questions