Submitted by dimitri_ru· Apr 18, 2026Process

Question

In a complex project with several subcontractors, one subcontractor reports a likely delay in the schedule. This could affect the other subcontractors and impact their ability to deliver on time. What should the project manager do first?

Options

  • AAssess the schedule and update the risk register.
  • BReport the delay to all other subcontractors.
  • CChange the milestones and sequence of work.
  • DEscalate to senior management and the stakeholders.

Unlock PMP to see the answer

You've previewed enough free PMP questions. Unlock PMP for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.

Topics

#Risk Management#Schedule Management#Project Monitoring#Impact Assessment