PMIPMI
PMP · Question #1048
PMP Question #1048: Real Exam Question with Answer & Explanation
Sign in or unlock PMP to reveal the answer and full explanation for question #1048. The question stem and answer options stay visible for context.
Submitted by femi9· Apr 18, 2026Process
Question
An experienced project manager is working on a complex hybrid project that has several dependencies with other projects. How should the project manager reduce the risk related to those external dependencies?
Options
- AAssess consolidated project plans for dependencies, gaps, and continued business value
- BDelegate the review of dependencies to the project sponsor and resource manager
- CSchedule a daily interproject review to track the progress of each project plan and their
- DAsk the project management office (PMO) to review the project plan dependencies
Unlock PMP to see the answer
You've previewed enough free PMP questions. Unlock PMP for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.
Topics
#Risk Management#External Dependencies#Project Integration#Inter-project Coordination