nerdexam
PMIPMI

PMP · Question #1014

PMP Question #1014: Real Exam Question with Answer & Explanation

Sign in or unlock PMP to reveal the answer and full explanation for question #1014. The question stem and answer options stay visible for context.

Submitted by skyler.x· Apr 18, 2026Business Environment

Question

A project manager acquired information from the market that would reduce the business value being delivered by an ongoing project. Based on that information, the project manager believes the project should be stopped. How should the project manager handle the situation?

Options

  • AHave a discussion with the project sponsor and cancel the project.
  • BRemove the items no longer applicable from the backlog and present the backlog to the project
  • CContinue working on the defined scope and review the risk matrix.
  • DHave a discussion with the sponsor and recommend the project business value be reassessed.

Unlock PMP to see the answer

You've previewed enough free PMP questions. Unlock PMP for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.

Topics

#Business Value#Project Governance#Sponsor Management#Strategic Alignment
Full PMP PracticeBrowse All PMP Questions