PMI
PMP · Question #1013
A project manager has been approached by the project sponsor about adding to the project scope. How should the project manager accommodate this request?
Sign in or unlock PMP to reveal the answer and full explanation for question #1013. The question stem and answer options stay visible for context.
Submitted by kev92· Apr 18, 2026Process
Question
A project manager has been approached by the project sponsor about adding to the project scope. How should the project manager accommodate this request?
Options
- ADisregard the request since the project scope is finalized
- BAdjust the project schedule to accommodate the new project scope requests.
- CCreate a change request for the change control board (CCB) to review.
- DUpdate the project team about the change request.
Unlock PMP to see the answer
You've previewed enough free PMP questions. Unlock PMP for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.
Topics
#Change Control#Scope Management#Integrated Change Control#Change Requests