nerdexam
PMIPMI

PMP · Question #1012

PMP Question #1012: Real Exam Question with Answer & Explanation

Sign in or unlock PMP to reveal the answer and full explanation for question #1012. The question stem and answer options stay visible for context.

Submitted by fatima_kr· Apr 18, 2026Process

Question

During a project's closing phase, the project manager identified that the client did not use one particular service. The client then asks the project manager to informally extend the service beyond the contract end date. The contract is clear about the expiration of the service. How should the project manager address this situation in order to close the project?

Options

  • AEscalate the request to the functional manager to approve the additional service hours.
  • BIssue a change request and activate the formal change control process to address the situation.
  • CAccept the client's proposal to use the service until the additional hours are exhausted.
  • DDeny the request and include it in lessons learned documentation for the next contract renewal.

Unlock PMP to see the answer

You've previewed enough free PMP questions. Unlock PMP for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.

Topics

#Change Control#Contract Management#Project Closure#Formal Processes
Full PMP PracticeBrowse All PMP Questions