nerdexam
PMI

PMI-SP · Question #257

PMI-SP Question #257: Real Exam Question with Answer & Explanation

Sign in or unlock PMI-SP to reveal the answer and full explanation for question #257. The question stem and answer options stay visible for context.

Question

You are the project manager for your organization. Your current project has a schedule variance of -$37,500 and a schedule performance index of 0.94. What do these values mean in regard to project performance?

Options

  • AYour project is likely to be late and over budget.
  • BYour project is performing well.
  • CYour project has a planned value of $600,000.
  • DYour project is six percent off schedule and has a considerable schedule variance.

Unlock PMI-SP to see the answer

You've previewed enough free PMI-SP questions. Unlock PMI-SP for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.

Full PMI-SP Practice