PMI
PMI-SP · Question #257
PMI-SP Question #257: Real Exam Question with Answer & Explanation
Sign in or unlock PMI-SP to reveal the answer and full explanation for question #257. The question stem and answer options stay visible for context.
Question
You are the project manager for your organization. Your current project has a schedule variance of -$37,500 and a schedule performance index of 0.94. What do these values mean in regard to project performance?
Options
- AYour project is likely to be late and over budget.
- BYour project is performing well.
- CYour project has a planned value of $600,000.
- DYour project is six percent off schedule and has a considerable schedule variance.
Unlock PMI-SP to see the answer
You've previewed enough free PMI-SP questions. Unlock PMI-SP for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.