PMI-SP · Question #243
You work as a project manager for BlueWell Inc. By referring to the figure given below, you along with your project team is calculating the latest completion of an activity. What is the latest your…
The correct answer is D. Day 30. Activity I can actually take all the way to Day 30 to complete. Note in the figure that Activity I does not need to be completed before Activity K can begin. This allows Activity I to take until Day 30 to complete as its late finish. Answer option C is incorrect. This is the…
Question
You work as a project manager for BlueWell Inc. By referring to the figure given below, you along with your project team is calculating the latest completion of an activity. What is the latest your project team can complete Activity I?
Exhibit
Options
- ADay 29
- BDay 26
- CDay 25
- DDay 30
How the community answered
(29 responses)- A3% (1)
- B7% (2)
- C17% (5)
- D72% (21)
Explanation
Activity I can actually take all the way to Day 30 to complete. Note in the figure that Activity I does not need to be completed before Activity K can begin. This allows Activity I to take until Day 30 to complete as its late finish. Answer option C is incorrect. This is the earliest Activity I may finish. Answer options B and A are incorrect. These are not the valid calculation.