PMI
PMI-SP · Question #241
PMI-SP Question #241: Real Exam Question with Answer & Explanation
Sign in or unlock PMI-SP to reveal the answer and full explanation for question #241. The question stem and answer options stay visible for context.
Question
You are the project manager of the NHQ Project. This project has a Budget at Completion of $750,000 and is expected to take 18 months to complete. The project is supposed to be 75 percent complete, but due to some errors the project is only 60 percent complete. At this time the project has spent $465,500. Management has asked you to review the project work and report the project's SPI. What is the SPI for this project?
Options
- A0.97
- B0.80
- C$562,500
- D-$112,500
Unlock PMI-SP to see the answer
You've previewed enough free PMI-SP questions. Unlock PMI-SP for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.