PMI-SP · Question #236

You work as a scheduler for your organization. You are developing a schedule and its constraints for the SAP project. There are nine inputs to develop a project schedule. Which of the following is…

The correct answer is A. Work breakdown structure. The WBS is not an input, directly, to the develop schedule process. Technically, you will need the scope baseline, which does include the WBS. The inputs in developing a schedule process are of nine types, which are as follows: Activity attributes Project schedule network…

Schedule Planning and Development

Question

You work as a scheduler for your organization. You are developing a schedule and its constraints for the SAP project. There are nine inputs to develop a project schedule. Which of the following is NOT an input to the schedule development process?

Options

  • AWork breakdown structure
  • BActivity attributes
  • CResource calendars
  • DActivity list

How the community answered

(38 responses)
  • A
    87% (33)
  • B
    3% (1)
  • C
    3% (1)
  • D
    8% (3)

Explanation

The WBS is not an input, directly, to the develop schedule process. Technically, you will need the scope baseline, which does include the WBS. The inputs in developing a schedule process are of nine types, which are as follows: Activity attributes Project schedule network diagrams Activity resource requirements Resource calendars Activity duration estimates Project scope statement Enterprise environmental factors Organization process assets

Topics

#schedule development#process inputs#PMBOK#WBS