You work as the project manager for BlueWell Inc. Mark, a project team member, has some doubts related to the outputs of the control schedule process. Which of the following is an output of the control schedule process?

Options

  • AProject schedule
  • BLessons learned
  • CChange request
  • DActivity resource requirement