PMI-SP · Question #221

You are the project manager for your organization. You have created the project schedule and have presented it to the management for their approval. Management decides to enforce resource leveling…

The correct answer is C. It will require additional resources if it is to finish in the same amount of time, as originally. Resource leveling heuristics limits the amount of time a resource is allowed to work in a given time period. This action typically increases the project duration. By adding additional resources to effort-driven activity the project can still complete, often, in the same…

Schedule Planning and Development

Question

You are the project manager for your organization. You have created the project schedule and have presented it to the management for their approval. Management decides to enforce resource leveling heuristics on your project schedule. What will likely happen to your project now?

Options

  • AIt will require fewer resources due to the cut in the project scope.
  • BIt will require additional resources for the additions to the project scope.
  • CIt will require additional resources if it is to finish in the same amount of time, as originally
  • DIt will require a new scope baseline to reflect the management change in the project approach.

How the community answered

(31 responses)
  • A
    3% (1)
  • B
    3% (1)
  • C
    84% (26)
  • D
    10% (3)

Explanation

Resource leveling heuristics limits the amount of time a resource is allowed to work in a given time period. This action typically increases the project duration. By adding additional resources to effort-driven activity the project can still complete, often, in the same schedule, otherwise the duration of the project will increase. Answer option B is incorrect. Resource leveling heuristics does not change the project scope. Answer option A is incorrect. This is not an instance of cutting the project scope. Answer option D is incorrect. The project scope baseline is not affected by resource leveling heuristics.

Topics

#resource leveling#schedule optimization#resource allocation#heuristics